Last weekend we poured the footings for the new posts we will be installing for the beefed up basement beam. On Friday, we purchased 5120 lbs of concrete mix, that’s 64 80 lbs bags or 2.5 tons or two loads in the sprinter. Luckily, the store was able to load the pallet right into the back of the sprinter with the fork lift so we only had to move each bag once. We hauled about 55 of those bags down into our basement. We rented a 3 cubic foot concrete mixer and on Saturday, we proceeded to mix 2 bag batches over and over again. After about 25 batches, all of our small graves were filled and we only had to return 13 bags to the store.
Over all, this project could have been a lot worse. Moving the concrete bags worked out alright and the little mixer we rented worked out well, especially fitting down our narrow basement stairs.
We were done with the concrete work on Saturday night and A. was able to finish up screwing up the heat transfer plates for the radiant heating and install insulation under the bathroom. We still have two bags of insulation left to install under the bedroom floor. We are holding off on this project to keep some heat toward the basement.
This weekend we plan on drilling the holes in the concrete that will hold the epoxy anchors for the post footings and ledger board that will hold the new beams on either side of the stairway. We won’t be able to do much else as we just ordered the supplies yesterday. With the extra time, we hope to work on some gas piping and electricity for the dryer. We realized this winter that drying laundry inside adds too much moisture to our house and that we end up running the dehumidifier to remove the moisture. Running an electric dehumidifier is more expensive that running a gas dryer so we decided to get a used dryer from a local appliance rehab place. With our super mild winter, we will probably be able to dry our laundry outside again in a few weeks but we might as well get this project done if we have the extra time.






































